Adeco Project Engineering BV West Africa Limited

Nigerian Breweries Plc Ama – New Brewhouse Electrical Installation

The Electrical installation of the new Meura brewhouse comprises 15 MCC panels, 14 Field panels, 64 motors, valves and instruments. The project implementation life cycle was 3 Months with a total team size of 25 Skilled and 13 semi-skilled workers.

    • Electrical Projects
    • Nigerian Breweries Plc
    • 2022

Overview

The Electrical installation of the new Meura brewhouse comprises 15 MCC panels, 14 Field panels, 64 motors, valves and instruments.

The project implementation life cycle was 3 Months with a total team size of 25 Skilled and 13 semi-skilled workers.

Outcome

The expansion enables the brewery to meet higher production volumes and provides a scalable solution to support future growth. This project not only addresses current production needs but also sets the stage for scalable and efficient operations.